Our Garage+ Project – Week Seven Update

Wow – we are almost two months into this building project now. This week (August 29 – September 4, 2021) was REALLY busy as you’ll see below. My photos focused on the more active stuff – so I hope you find them and the continuing saga of this project interesting.

First, I was able to get some shots on the interior work on the second floor.

Jon and and Jonny Victor (the father and son team of Ready Installs) showed up early to check out the project’s progress.

Jonny checking out door height.

Next, the first order of business on Monday, August 30th, was to get the deck header up. This involved installing an ice-water barrier (which the crew decorated with a muscle-man drawing of Raphael as it will never be seen again), and nailing the header.

Inside the garage, work on installing furring in the ceiling went on.

Early furring work in garage

At this point, we had a need to get some construction synchronized dance going. To start the deck we needed get the piers in for the deck – which required excavation and careful measurement. Also, the septic line needed to be started. Andy Cormier returned with his excavator and crew to do this. There were quite a few roots in the ground from a previously removed pine tree.

Once the trench was right, each 600-lb. pier was put in, and checked for accurate placement.

After this, Andy backfilled the trench.

Monday August 30th progress.

On Tuesday, August 31st, work continued apace. The framing of the deck began as well as work on a septic line and more.

When Andy was safely done, work could get going on the deck supports. Temporary supports were used and then the main deck supports were attached to the piers.

The sun sets on Tuesday’s progress.

Wednesday saw more of the same – deck progress. I was out so I did not get as many photos. The crew had to wrap it up early as the remnants of Tropical Storm Ida were coming with heavy rain predicted Wednesday-Thursday.

The crew here is framing up the deck roof overhang as Jonny gets the stairway landing area identified and cleared.
A shortened day (Sep 1st) with progress on the stairs and the deck area clear here.

Ah, but the rain came heavy – BUT – it was only overnight and gone by the morning of Thursday September 2nd – so happily work could continue on the deck and second floor in preparation for Saturday roofing.

Yay – work can go on!
Interior framing progress.
View of the stair stringers and temporary cross bracing.
Thursday mid-day progress was strong – deck roofing overhang was nearly done.
End of day Thursday had the roof all enclosed and ready for the roofers. The boards on the deck are temporary supports for the crews.

No construction happened Friday as the roofing crew was going to hit the ground running on Saturday. And hit the ground early they did at 7 AM!

Sun coming up on the roofing crew on Saturday, September 4th.

The roofing crew was done in 4 hours – and now we are ready for another good week. We did also work o Saturday with one of Jon’s patio specialists to define what our patio would look like and that should be very exciting and gorgeous – but you’ll have to wait to see that (like us).

All roofed in!

Thanks for taking a look here – and what do you think of the progress so far? We have a good ways to go, and as the Starks (and EVERY New Englander) says, “Winter is Coming”…so we are certainly wanting sooner than later.

For those of you who are wondering if I will EVER get back to hobby stuff, I will. I am using some time to rewrite and add onto my Aztec supplement for Buck Surdu’s Feudal Patrol™ in Mesoamerica (Civilizations Collide). New and improved (I hope).

Also, I am writing a good number of scenarios too. Plus, golf season is winding down in the next six weeks, so that’s happening too.

Go to Source

Author: Mark Morin

Leave a Reply

Your email address will not be published. Required fields are marked *